Contract – costs – primary judge gave judgment in respondent’s favour in proceedings – primary judge found appellant had repudiated Supply agreement between parties and awarded damages to respondent – finding of repudiation depended on primary judge’s acceptance that, on proper construction of Supply Agreement, appellant was obliged to order certain articles from respondent exclusively – appellant challenged primary judge’s construction of contract, and costs order in respondent’s favour – respondent cross-appealed against primary judge’s rejection of its claim for breaches by appellant of subsequent agreements – construction of Supply Agreement and documents accompanying it – implied terms – held: appeal and cross-appeal dismissed.